Metro Train Track concreting done Vadapalani- Koyambedu

Posted on: 08/Mar/2013 11:11:34 AM
Between Vadapalani and Koyambedu station a total of 9944 meter plinth track concreting work was completed and 7500 meter track laying work too was completed. Welding work for 1650 joints have been done. The railways handed over 6000 meters of track-work other contractors, according to sources.