Metro Rail Work progress of Vadapalani Station

Posted on: 11/Jun/2013 6:34:56 PM
The Vadapalani Elevated station civil works are fast progressing with several works such as Pile, Pile cap , Stub Column, Plinth beam at street level, Column up to concourse level(1st lift), Column up to concourse level (2nd lift) and I Girder Erection have been completed.

And 50 out of 73 no of column up to platform level and 9 out of 14 no of parapet wall have been erected. 1460 out of 2500 no of concourse floor slab, 11 out of 16 no of deck Slab and 1570 out of 3000 no of link bridge level slab have been casted as on date

Source : CMRL