Ganeshapuram Road Over Bridge Construction Resumes: Chennai Bridge Expected to Open by March-April 2027

Updated: 27/Nov/2026 9:53:52 AM
930 views
Ganeshapuram Road Over Bridge Construction Resumes: Chennai Bridge Expected to Open by March-April 2027

Construction work on the long-delayed Ganeshapuram Road Over Bridge (ROB) in Chennai has gained momentum, with the Greater Chennai Corporation (GCC) beginning preliminary works for the installation of its main girder.

Civic officials expect the bridge to be completed by March or April 2027, provided the remaining approvals are received on time.

75% of the Project Completed

The Rs. 226.55-crore Ganeshapuram ROB project has reached approximately 75% completion, according to Greater Chennai Corporation officials.

The Southern Railway (SR) has granted permission for the preliminary structures required for the girder installation. However, approval for the permanent girder work is still being processed.

Since the installation will take place above an operational railway track, a scheduled power block will be required. Southern Railway officials have stated that the necessary arrangements will be made at the earliest.

58-Metre Bowstring Girder Arriving at the Site

The project involves installing a 58-metre-long bowstring girder, with components being transported to the construction site from Pudukkottai.

A senior official has also been appointed to monitor the project`s progress and coordinate the remaining construction activities.

The GCC expects to complete the bridge by March or April 2027 if all outstanding permissions are secured without further delays.

Residents Welcome Resumption of Construction

T.K. Shanmugam, president of the Federation of North Chennai Residents Welfare Associations (FNRCWA), welcomed the resumption of girder-related work.

He said residents had demanded the immediate commencement of the girder installation and expressed satisfaction that construction had finally resumed.

He also pointed out that the project, which began in January 2023 with an initial two-year completion deadline, had faced delays due to land acquisition issues and the relocation of utility cables.

Residents have expressed concerns over repeated deadline extensions and the increasing traffic congestion in the area. They have urged the GCC to complete the project and open the bridge to the public within the newly announced March-April 2027 timeframe.

Project Highlights

- Project: Ganeshapuram Road Over Bridge (ROB)

- Implementing agency: Greater Chennai Corporation (GCC)

- Project cost: Rs. 226.55 crore

- Construction started: January 2023

- Current completion: Approximately 75%

- Main girirder: 58-metre bowstring girder

- Railway authority: Southern Railway

- Expected completion: March-April 2027

The completion of the Ganeshapuram ROB is expected to help ease traffic congestion and improve connectivity for residents of North Chennai.