Chennai Anna Salai Steel Flyover: 50 of 69 Pillars Completed, When Will the Remaining Work Finish?

Updated: 16/Nov/2026 1:01:41 PM
760 views
Chennai Anna Salai Steel Flyover: 50 of 69 Pillars Completed, When Will the Remaining Work Finish?

Chennai Anna Salai Steel Flyover Update: The ₹621-crore, 3.2-km elevated corridor between Saidapet and Teynampet is nearing completion, with 50 of its 69 pillars already constructed. However, work above the Nandanam and Teynampet Metro stations requires a revised engineering approach. The Chennai Metro Rail Limited (CMRL) has now set March 2027 as the target for completing the project.

Chennai Anna Salai Steel Flyover Project Nears Completion

A major infrastructure project aimed at easing traffic congestion on Chennai`s busy Anna Salai is progressing towards its final stages. The four-lane steel flyover, being constructed at an estimated cost of ₹621 crore, will extend approximately 3.2 kilometres from Saidapet to Teynampet.

One of the project`s key features is that nearly 2.4 kilometres of the flyover runs directly above an existing underground Metro rail corridor. This makes it the first flyover of its kind in India to be constructed directly over an operational underground Metro route.

Once opened, the elevated road is expected to reduce congestion at seven major junctions, including CIT Nagar, Nandanam and Eldams Road. Commuters could potentially complete a journey that currently takes around 30 minutes in just five minutes.

50 of 69 Steel Pillars Have Been Installed

Construction has been carefully planned to protect the underground Metro tunnel, which runs approximately 14 to 15 metres below the road surface. Accordingly, the flyover`s foundation has been restricted to a depth of around seven metres.

Instead of conventional concrete structures, the project uses lightweight, specially designed steel pillars and girders manufactured in Hyderabad. These components are transported to Chennai and assembled at the construction site.

So far, approximately 2.3 kilometres of the flyover work has been completed, with 50 of the total 69 pillars installed.

Several important stretches have also been connected, including sections from the Saidapet starting point towards the T. Nagar junction, the former Volkswagen showroom and the Buhari Hotel area. Steel slabs have also been installed near the Royal Enfield showroom.

Why Was Construction Delayed Near Nandanam and Teynampet?

Despite the progress, construction above the Nandanam and Teynampet underground Metro stations had remained suspended for several months.

The original design proposed three pillars, with one in the middle of the road and two on either side. However, placing a central pillar above an operational Metro station raised space and safety concerns.

To address the issue, CMRL approved an alternative engineering design known as the Portal Frame method in October 2026, following a recommendation from a Japanese consultant.

Portal Frame Technology to Resolve Construction Challenges

Under the revised d design, two pillars will be constructed on either side of the Metro station, using the station walls as supporting locations. A cross beam will connect the pillars, allowing the flyover structure to pass overhead without requiring a central pillar.

This arrangement will be implemented across approximately 300 metres above the Nandanam and Teynampet Metro stations, with portal frames planned at intervals of every 15 metres.

The design is intended to preserve road width while preventing additional pressure on the underground Metro stations.

At present, girders still need to be installed on the steel pillars near Nandanam. Work on the portal frames near Teynampet Metro station is also yet to begin.

When Will the Anna Salai Flyover Open?

Working above operational Metro train services comes with restrictions. Construction teams are permitted to work for only six hours a day in these sections.

As a result, completing the portal frame structures is expected to take another three to four months. Considering these requirements, CMRL has set March 2027 as the revised target for completing the entire flyover project.

Once operational, the Saidapet-to-Teynampet steel flyover is expected to provide significant relief to motorists travelling along Anna Salai, one of Chennai`s busiest commercial and office corridors. Commuters are now waiting for work above the two Metro stations to progress so that the long-awaited infrastructure project can become fully operational.