Chennai Metro Milestone: Six Trains to Pass Through Kathipara Junction Simultaneously by 2027

Updated: 27/Nov/2026 11:13:07 AM
324 views
Chennai Metro Milestone: Six Trains to Pass Through Kathipara Junction Simultaneously by 2027

Chennai is set to witness a major milestone in its metro rail expansion, with six metro trains expected to operate simultaneously through Kathipara Junction by March 2027. The trains will run across three corridors, covering two routes under Phase I and one under Phase II.

The development marks significant progress in the construction of Chennai Metro Rail`s (CMRL) ambitious Phase II network.

Phase II Viaduct Construction Completed at Kathipara

The long-awaited balanced cantilever construction work at Kathipara Junction has been completed, paving the way for the next stage of the project.

The newly constructed viaduct will allow two additional metro trains to travel from Koyambedu to Alandur, passing over the junction`s tallest pillar, which stands 108 feet tall.

The 14.5-km Koyambedu-Alandur stretch forms part of Corridor 5 of Phase II, which connects Madhavaram to Sholinganallur via Alandur.

The Phase II network, once completed, will cover a total distance of 118.9 km.

Special Construction Technique Used to Avoid Traffic Disruptions

CMRL adopted the balanced cantilever construction method at Kathipara Junction to build the elevated viaduct without causing major traffic diversions.

The construction involved building a massive 413-metre circular viaduct section above the cloverleaf-shaped Kathipara flyover and the two operational Phase I metro corridors.

The structure extends from Paul Wells Road to Alandur and includes some of the tallest pillars in the Chennai Metro network, ranging from 88 feet to 108 feet.

The new alignment also features a particularly sharp curve with a radius of just 125 metres.

Train Trials Expected to Begin in January 2027

According to CMRL officials, track installation work has already started along the newly completed balanced cantilever section.

The track work is expected to be completed within 45 days. Following this, metro train trials are scheduled to begin by early January 2027.

Once the necessary testing and other procedures are completed, the new stretch will move closer to passenger operations.

Construction Faced Several Challenges

The viaduct construction, originally scheduled for completion in February 2026, experienced multiple delays due to challenging site conditions.

CMRL officials cited several difficulties, including:

- Limited working hours: Construction activities were permitted only during restricted hours.

- Proximity to operational metro lines: The new viaduct runs very close e to the existing Phase I corridors.

- Complex curved construction: Each viaduct segment had to be constructed on-site because of the curved alignment.

- High-voltage electrical equipment: Construction machinery and materials were close to high-voltage power lines and the Phase I overhead electrical systems.

Workers had to carry out critical construction activities between midnight and 4:00 AM, requiring the Phase I overhead electrical equipment to be switched off during those hours.

The curved structure also made concrete segment alignment and stressing operations more complicated due to friction-related challenges.

Despite these difficulties, the completion of the balanced cantilever section marks an important step towards integrating Chennai Metro`s Phase II network with its existing infrastructure.

A New Milestone for Chennai Metro

With the completion of this major construction work, Kathipara Junction is preparing for a significant transformation.

By March 2027, six metro trains are expected to pass through Kathipara Junction simultaneously across three corridors, strengthening connectivity and marking another important stage in Chennai`s expanding metro rail network.