Following the immense response and usefulness of Metropolitan Transport Corporation’s small buses, 100 more are in pipeline to rock the city roads in three months down the line.
CMRL to commence its services from March
...........................................................................................................................
The 18th Metro Rail coach arrived at Koyambedu Depot. Efforts are being taken to commence the services to St Thomas Mount from March onwards.
Chennai Metro Rail project activities are under progress in Shenoy Nagar. A house in this locality suddenly sank by 2.5’. This has caused some commotion in the area.
Metro Rail Project officials have informed that there are good prospects of commencing the new metro rail projects planned in 3 sectors – Madhavaram-Velachery, Madhavaram-East Coast Road, and Koyambedu-Mylapore Luz.
60-70 per cent of the work on the underground stretch is completed and the tunnels from Thirumangalam to Egmore are expected to be ready by February-end.
17th Metro Train arrives in Chennai!
...........................................................................................................................
Out of the total of 42 trains for Chennai Metro Rail Project, the 17th Train arrived at Koyambedu workshop by road.