Kumari Palany & Co

No. of views : (1936)

Washarmenpet Tunneling Work on Underground Railway yet to be finished

Posted on: 04/Jan/2013 3:38:14 PM
The major concerning process of underground rail project was yet to be finished soon and to be launched shortly after the current year completion and the work is finished shortly through skilled Labours. The tunnel work is based on ring installation where the Train passe through. As on Date the 1st TBM Drive at Washemanpet has completed 227 rings at an average of 6.5 rings per day . The TBM has crossed the MES land and entered into residential area. 1st TBM is expected to reach next station Mannadi by March 2013.And as per the Date the 2nd TBM drive has completed 46 rings at an average of 3.0 rings.

The underground trains are yet to be launched soon and the train equipment are imported from the leading foreign company.by the officials information the transportation will begin from 2014.